Photovoltaic Glass Cold Repairs and Restarts Bring Electric Boosting Electrode Restocking Forward
WeiBeam · Electrode solutions for high-temperature melting
Cold repairs and restarts of photovoltaic glass lines are clustered, and the inspection and restocking of electric boosting molybdenum electrodes are being moved ahead of ignition. The article reviews cold repair schedules, electrode inspection checkpoints and points to watch during the restart ramp-up.
Entering the fourth quarter, cold repair and restart schedules for photovoltaic glass lines are relatively dense. Some furnaces are re-ignited after cold repair, electric boosting systems resume operation, and restocking and spare-part confirmation for molybdenum electrodes are completed before ignition. Unlike new lines, cold repair projects place more emphasis on specification match and arrival timing.
Why Cold Repair Windows Cluster at This Time
Photovoltaic glass furnaces usually run continuously for several years, and a cold repair requires shutting down, draining the glass melt and replacing refractories and some electrodes. Companies tend to schedule the work when order flow is relatively flat and module production pressure is lower, in order to shorten the ramp-up after restart. Once the cold repair plan is fixed, purchasing, construction and ignition dates lock together, and the cost of a late electrode is magnified.
The First Check After Furnace Teardown
After the spent electrodes are removed, check actual dimensions, thread condition and degree of oxidation, and judge which are normal consumption and which relate to operating conditions. If local bending or abnormal end erosion is found, investigate current distribution and melt level control so that the problem is not repeated once the new electrodes are installed.
| Item of concern | Typical values and notes |
|---|---|
| Common specifications | Rod diameter Φ20–100mm, length 150–1500mm (custom sizes available to drawing) |
| Applicable standards | YS/T 1312-2019 Molybdenum Electrodes; molybdenum rods per ASTM B387 / GB/T 17792, molybdenum plates and discs per ASTM B386 / GB/T 3876 |
| Operating temperature | Approximately 1300°C continuous, short-term ceiling approximately 1600°C |
| Operating current density | 1–3A/cm² |
Confirmation at the Masonry and Installation Stage
Before the electrodes are installed, confirm the reserved openings in the brickwork, the clearance of the water-cooling jacket and the sealing method, because dimensional deviation directly affects how difficult replacement will be. For furnaces with water-cooled structures, also check that the water circuit is clear and that flow and temperature monitoring have returned to normal, so that the end is not damaged by insufficient cooling after ignition.
Power Supply Review Before Ignition
The power supply system should be reviewed for transformer capacity, busbar connections and control logic, and the power distribution plan for the ramp-up stage confirmed. The initial electrode load should not be applied in full at once; it is usually raised step by step along a staged heating curve, watching whether melt temperature and current change in step.
What to Watch After Restart
During ramp-up, electrode load and melt surface temperature fluctuate considerably, so it is advisable to record daily current, voltage and cooling water temperature to build a comparable operating baseline. If one electrode draws a noticeably higher current, investigate contact resistance and clamp condition early rather than waiting for a furnace stop.
Product parameters are given in the selection notes for this duty; you can also visit the electrode manufacturer's home page.
Frequently asked questions
What does confirmation at the masonry and installation stage cover?
Before installation, confirm the reserved openings in the brickwork, the clearance of the water-cooling jacket and the sealing method, because dimensional deviation directly affects how difficult replacement will be. For water-cooled furnaces, also check that the water circuit is clear and that flow and temperature monitoring have returned to normal, so that the end is not damaged by insufficient cooling after ignition.
What is the focus of the power supply review before ignition?
The power supply system should be reviewed for transformer capacity, busbar connections and control logic, and the power distribution plan for the ramp-up stage confirmed. The initial electrode load should not be applied in full at once; it is usually raised step by step along a staged heating curve, watching whether melt temperature and current change in step.
Why do cold repair windows cluster at this time?
Photovoltaic glass furnaces usually run continuously for several years, and a cold repair requires shutting down, draining the glass melt and replacing refractories and some electrodes. Once the plan is fixed, purchasing, construction and ignition dates lock together, and the cost of a late electrode is magnified.
Note: this article shares general industry and technical information and is not purchasing, investment or legal advice. Specific parameters and results are governed by the mutual technical agreement and factory inspection records.
Related products
Electrodes and high-temperature molybdenum parts for this duty — specifications and selection notes are on the product pages.
Product information

Glass melting furnace molybdenum electrode
For electric boosting and all-electric melting of container, packaging, pharmaceutical, photovoltaic and electronic glass, compatible with mainstream refractories and furnace designs.
View specifications →
Molybdenum disc
Circular sheet made from high-purity molybdenum powder by powder metallurgy and rolling; used for furnace heating elements, heat shields, boats and sputtering targets.
View specifications →
Molybdenum rod and shaft
Rod and shaft diameters beyond wire: Ø0.5–25mm drawn or swaged shafts and Ø16–300mm forged or sintered rods, for vacuum electronics, guide rods, electrodes and heating elements.
View specifications →